Delivery of a complete renovation of the electrical wiring for the paint shop’s overhead conveyor system, including a new control system. This conveyor was put into operation in 1978 and had been functioning without problems, but over the course of 30 years, the control system had become somewhat outdated, and a renovation was necessary. After evaluating the current condition, the equipment was found to be mechanically sound, except for the stops, which also needed to be replaced. From an electrical standpoint, a complete replacement was necessary.
Environment
- paint shop
Interesting facts
The renovation took place while the paint shop was partially operational. The total shutdown lasted only three weeks, during which we worked around the clock to get everything done on time.